ČERNAY AGRO
Complex implementation of 100kWp photovoltaic system
Projection
Projection
Photovoltaic power plant with installed power of 100 kWp achieves annual solar gain of 104 MWh.
From the total annual consumption 0 MWh the PV system will save 48 %
Total consumption of CO₂ emissions of volume 13.392 kg will be reduced by 6.433 kg which represents the volume of emissions that has to be absorbed 321 mature trees.
Annual electricity costs of 26.784 Eur are lowered by more than 12.867 Eur
Return of investment achieved 5 years 9 months.