ČERNAY AGRO
Complex implementation of 100kWp photovoltaic system
Projection
Projection
Photovoltaic power plant with installed power of 99 kWp achieves annual solar gain of 109 MWh.
From the total annual consumption 1.274 MWh the PV system will save 9 %
Total consumption of CO₂ emissions of volume 135.044 kg will be reduced by 11.456 kg which represents the volume of emissions that has to be absorbed 572 mature trees.
Annual electricity costs of 256.503 Eur are lowered by more than 23.777 Eur
Return of investment achieved 4 years .